Week 2: Production timeline and script rework

So after garnering feedback on Monday it was decided that I should re-work my script and keep the setting contained within a house. Same gags apply, just on a different scale. I also finalized my production schedule so hopefully I'll be able to keep to that. I'll cross things out as I go to keep myself on track.

Week 1

  • story pitch, script


Week 2

  • revise script
  • finish character design
  • finish layouts/background concept
  • storyboard thumbnails


Week 3

  • storyboard
  • animatic w/ scratch sound
  • plan for final sound


Week 4

  • production (lines)


Week 5

  • production (lines/color)


Week 6

  • production (color)


Week 7

  • compositing


Week 8

  • compositing
  • sound


Week 9

  • sound
  • final touch-ups


Week 10

  • class submission & critique
  • revisions
  • submit to screenings on Friday
According to my schedule, I should be done with character art, layout, and thumbnails by the end of this weekend so I'll probably make a post containing most of that on Sunday.